Photos: Punchbowl Mosque Construction Timeline

Donate

Wednesday 12 April 2017 (external walls revealed; scaffolding removed)

Construction-120417-2 Construction-120417-1

Wednesday 5 April 2017 (muqarnas mini-domes and main dome with concrete rings)

Construction-050417-2 Construction-050417-1

Wednesday 15 March 2017 (Underfloor hydronic heating and cooling system installed)

Construction-150317-1 Construction-150317-2

Thursday 2 March 2017 (Dome interior and Muqarnas fully visible)

Construction-020317-2 Construction-020317-1

Wednesday 1 March 2017 (Dome and Muqarnas form work being stripped away)

Construction-010317-2 Construction-010317-1

Friday 24 February 2017 (Dome roof and Mosque entry taking shape)

Construction-240217-2 Construction-240217-1

Thursday 2 February 2017 (Dome and Mosque roof being installed)

Construction-020217-2 Construction-020217

Wednesday 25 January 2017 (roof metal beams installed)

Construction-240117-4 Construction-240117-3

Wednesday 18 January 2017 (car park and toilets)

Construction-180117-2 Construction-180117-1

Construction-240117-2 Construction-240117-1

Wednesday 21 December 2016 (Dome steel frame installed)

construction-211216-5 construction-211216-6

 

PMC-Dec16-2 PMC-Dec16-6

Tuesday 13 December 2016 (Muqarnas perspex moulds stripped away)

construction-131216-2 construction-131216-1

Monday 28 November 2016 (concrete to the Dome base ring completed)

construction-281116-1 construction-281116-2

Thursday 24 November 2016 (Concrete being poured into the Dome base)

construction-241116-2 construction-241116-1

Saturday 19 November 2016 (Dome base insulation, steel and Minaret roof concreted)

construction-191116-2 construction-191116-1

Saturday 12 November 2016 (Dome ring concrete and Roof steel)

construction-121116-4 construction-121116-3

Saturday 12 November 2016 (ablution block taking shape)

construction-121116-2 construction-121116-1

Saturday 5 November 2016 (steel being fitted for the Mosque dome)

construction-051116-2 construction-051116-1

Wednesday 2 November 2016 (ablution concrete wall constructed)

construction-021116-2 construction-021116-1

Friday 28 October 2016 (Clr Khodr Saleh site visit)

construction-281016-2 construction-281016-1

Tuesday 25 October 2016 (dome form work being built)

construction-251016-2 construction-251016-1

Wednesday 19 October 2016 (muqarnas rows concreting completed)

construction-191016-1 construction-191016-2

Tuesday 11 October 2016 (last two muqarnas rows being built)

construction-111016-1 construction-111016-2

Wednesday 5 October 2016 (further extension of the roof muqarnas)

construction-051016-3 construction-051016-4

Wednesday 5 October 2016 (toilet blocks being built)

construction-051016-2 construction-051016-1

Saturday 17 September 2016 (mezzanine 2 walls and more muqarnas rows being prepared)

construction-170916-2 construction-170916-1

Saturday 10 September 2016 (second mezzanine floor slab concreted)

construction-100916-2 construction-100916-1

Wednesday 7 September 2016 (additional rows of muqarnas moulds installed)

construction-070916-2 construction-070916-1

Wednesday 31 August 2016 (two rows of Mosque muqarnas and internal wall extensions concreted)

Construction-310816-2 Construction-310816-1

Wednesday 17 August 2016 (Mosque muqarnas moulds and level 1 walls)

Construction-170816-2 Constructiuon-170816-1

Monday 8th August 2016 (Mosque mezzanine 1 slab done; internal walls next)

Construction-080816-1 Construction-080816-2

Tuesday 26th July 2016 (Muqarnas prototype completed)

Construction-260716-1  Construction-260716-2

Saturday 16th July 2016 (complex Mosque ceiling 99 muqarnas being constructed)

Construction160716-1 Construction160716-2

Saturday 9th July 2016 (Mosque ceiling muqarnas formwork being prepared)

Construction-090716-2 Construction-090716-1

Tuesday 28 June 2016 (concrete build of Mosque walls continue)

Construction-280616-2 Construction-280616-1

Tuesday 21 June 2016 (Mosque walls being built with concrete poured)

Construction-210616-1  Construction-210616-3

Wednesday 8 June 2016 (formwork for Mosque walls being constructed)

Construction-080616-1 Construction-080616-2 Construction-080616-3 Construction-080616-4

Sunday 29 May 2016 (ground floor slab complete)

Construction-290516-1 Construction-290516-2

Wednesday 25 May 2016 (ground floor concreting continues)

Construction-250516-1 Construction-250516-2

Tuesday 24 May 2016 (pouring of ground floor concrete)

Construction-240516-2 Construction-240519-1

Thursday 19 May 2016 (ground floor steel installation)

Construction-190516-2 Construction-190516-1

Monday 16 May 2016 (ground floor prep for concrete)

Construction-160516-1 Construction-160516-2

Monday 2 May 2016 (ground floor decking)

Construction-020516-2 Construction-020516-1

Friday 15 April 2016 (level 1 car park decking)

150416-1 150416-2 150416-3 150416-4

 

Friday 8 April 2016 (level 2 car park slab)

110416-3 110416-2 110416-1

Sunday 27 March 2016 (Formwork decking, slab, 2nd ramp)

IMG_2_270316 IMG_270316

Friday 19 February 2016 (ramp completed with support pillars)

IMG_3530 IMG_3532 IMG_3533 IMG_3537

 

Tuesday 12th January 2016 (concrete pour on car park ramp)

IMG_3311 IMG_3313 IMG_6680 IMG_6684

 

Monday 21st December 2015 (Digging second level; ramp concrete)

IMG_2749 IMG_2750 IMG_2747 IMG_2748

 

Monday 14th December 2015 (Laying concrete ramp to car park)

IMG_2674 IMG_2676 IMG_2678

 

Friday 11th December 2015 (Anchoring and Shoring)

FullSizeRender4 FullSizeRender1 FullSizeRender3 FullSizeRender2

 

Friday 4th December 2015 (Shoring)

IMG_2926 IMG_2925

 

Sunday 29th November 2015 (Excavation continues)

IMG_2618 IMG_2617

 

Thursday 29th October 2015 (Official Groundbreaking Ceremony)

IMG_2620 IMG_2619

 

Monday, 26th October 2015 (Works commence)

IMG_2622 IMG_2621